Project Timeline

.....................................................................................................................
2010 - Present
Environmental Impact Assessment
.....................................................................................................................
February 2013
Submission of Scoping report to Highland Council
.....................................................................................................................
Autumn 2013
Public consultation commenced with a Community Council meeting
held in Watten in October, with the possibility of another later in the
year. An initial public exhibition will be held in Watten in October to
show the proposed plans. Subsequent public exhibitions will take place after consultation feedback is incorporated into the project design.
.....................................................................................................................
Winter 2013
Incorporate findings of EIA and consultation feedback
.....................................................................................................................
Summer 2015
Submit Planning Application for consent to the Highland Council
.....................................................................................................................
Summer 2016
Submit further ornithological survey results to Scottish Natural Heritage
.....................................................................................................................
July 2017
Planning permission granted by The Scottish Government
.....................................................................................................................
Autumn 2018
Public consultation for amended wind farm proposal