Project Timeline

.....................................................................................................................

2010 - Present

Environmental Impact Assessment

.....................................................................................................................

February 2013

Submission of Scoping report to Highland Council

.....................................................................................................................

Autumn 2013

Public consultation commenced with a Community Council meeting

held in Watten in October, with the possibility of another later in the

year. An initial public exhibition will be held in Watten in October to

show the proposed plans. Subsequent public exhibitions will take place after consultation feedback is incorporated into the project design. 

.....................................................................................................................

Winter 2013

Incorporate findings of EIA and consultation feedback

.....................................................................................................................

Summer 2015

Submit Planning Application for consent to the Highland Council

.....................................................................................................................

Summer 2016

Submit further ornithological survey results to Scottish Natural Heritage

.....................................................................................................................

July 2017

Planning permission granted by The Scottish Government 

.....................................................................................................................

Autumn 2018

Public consultation for amended wind farm proposal